Current cost of new EDDC HQ at Honiton/Exmouth – nearly £10m and all meetings assuming Pegasus gets its planning permission are already scheduled

Relocation cost so far:

£9,726,455

Click to access 6-project-report-20-300915.pdf

page 5

Further on in the report:

The project has
7 “red risks”
32 “orange risks” and
8 “blue risks”

They already have a pretty good idea of when the planning meeting for Pegasus will be and have scheduled it

12 July 2016 (page 12)

and have already fixed an Extraordinary Cabinet Meeting
on 27 July 2016
and a similar Full Council meeting for
3 August 2016
with works in Exmouth to start on 4 August 2016.

Of course, all these meetings take place in the major summer holiday period.

Relocation to Exmouth Town Hall will take place on
20 June 2017
and full relocation to both sites will be achieved by
25 September 2017.

Thereafter the report consists of various cost breakdowns.

It appears that, for some reason, Appendix C is missing

One thought on “Current cost of new EDDC HQ at Honiton/Exmouth – nearly £10m and all meetings assuming Pegasus gets its planning permission are already scheduled