Has EDDC’s new Manstone depot satellite office block been included in relocation costs?

The following Freedom of Information request implies that the cost may not have been included, but we shall see, we hope.

Owl wonders why just one set of employees has been left in Sidmouth in brand new offices and why they could not be accommodated on the Honiton site or the Exmouth site. Surely, THREE sets of offices will be MUCH more expensive to run than one HQ? But cost barely seem to concern Tory councillors, who seem to feel there is little need to scrutinise them.

“Laissez les bons temps rouler!”

“Dear Ms Symington,

I would like to make a formal request under the Freedom of Information Act 2000. I am also making this request under the Environmental Impact Regulations 2004 which require disclosure on the part of Local Authorities.

On 22nd December, I corresponded with the Planning Department with regard to the Council’s planning application for offices for its Estates Department at the Manstone Depot in Sidmouth: https://planning.eastdevon.gov.uk/online…

Several of my questions were answered, but not the following:

“The site is now clearly part of the District Council’s relocation project. This application represents the relocation of one of the key departments from the Knowle site – and yet there has been no mention in the Moving and Improving site pages: http://eastdevon.gov.uk/moving-and-impro…
“And I am unable to find any other information about this relocation of the Estates Department elsewhere.”

Could you provide me with any such references to this project (other than the planning application itself), either as documentation or weblinks.

And could you provide me with the full and exact costings for this planning application: the building costs of the new offices and where the finance for this project will be coming from.

On 9th January, the District Council stated the following to the press:

“The transfer of depot activities is an existing costed element of the relocation project and, as such, included within the independent and positive cost modelling of relocation.”
http://www.sidmouthherald.co.uk/news/dis…

Could you provide me with the documentation which shows how the transfer of depot activities is an existing costed element of the relocation project.

And could you indicate exactly where this information is located within the independent and positive cost modelling of relocation.

I would be grateful if you could answer the four stipulated questions above.

Thank you.
I look forward to hearing from you.
Yours faithfully,
Jeremy Woodward
Sidmouth”

https://www.whatdotheyknow.com/request/costing_the_relocating_of_the_es