From an article in today’s Daily Telegraph about the omnishambles that is the Swansea Tidal Lagoon project:

“… But another battle was raging over the developers’ plans to create a huge “super-quarry” on the Lizard Peninsula in Cornwall, from which they hoped to ship 1.5 million tons a year of the stone needed to build the six-mile long breakwater round Swansea Bay.

A case brought on behalf of local protesters argued that the planning permission rushed through Cornwall Council last April had broken the law by failing to include an environmental assessment of the potential damage the quarry would do to a whole range of natural sites officially designated for special protection.

Although just before Christmas Mr Justice Dove in the High Court ruled that the permission had been given illegally, it is only now his judgment has been published we can see just how damning it was to the council’s conduct in every way.

It also emerges that the planning officer responsible had been involved in two earlier decisions where Cornwall approved applications for two highly controversial wind farms.”

http://www.telegraph.co.uk/comment/columnists/christopherbooker/12103688/Mad-Swansea-tidal-lagoon-scheme-heading-for-the-rocks.html

More information on the judge’s scathing commented is here: