Hinkley C: the damning views of its own French engineers

EDF dissenters urge Hinkley nuclear delay

nicosiamoneynews.com Wednesday, March 30, 2016

Senior engineers at French utility EDF have called for at least a two year delay at the controversial Hinkley Point nuclear project in the UK and recommended a redesign of the reactor technology.
An internal white paper written by dissenting EDF engineers, which has been seen by the Financial Times, argues that Hinkley Point is so complex and untested that the company should announce a later completion date than the target of 2025.

The paper, circulated among top executives, said that the “realistic service date was 2027” due to the size of the project, continuing design modifications to the European Pressurised Reactor system and the “very low” competency of French supplier Areva in making some of the large components.
The white paper also made the case for a “new EPR”, calling on the company to redesign the current reactor technology to make it smaller, cheaper to build and less complicated.

A timely start-up at Hinkley Point, which will provide 7 per cent of UK electricity, is critical because the government has set 2025 as the date by which the last of Britain’s coal-fired power stations is due to close.
EDF said in a statement last night that it would stick to the planned timetable. “The date for the first operation of Hinkley Point C has not changed. It will be in 2025,” it said.

But experts say any slippage in that timetable was likely to mean having to pay companies to keep older plants running or even build more short-term, highly polluting diesel power.

EDF has been beset by internal tensions over Hinkley Point, with chief financial officer Thomas Piquemal resigning this month over concerns that the project could threaten the company’s future.

Critics have raised concerns over the £18bn cost, given EDF’s stretched balance sheet. Two other projects in France and Finland using the same EPR technology are both severely delayed and billions over budget.

The unsigned white paper was written after Mr Piquemal’s resignation by a group of senior engineers and other dissidents, according to people with knowledge of the document. The company plans to make the final investment decision on the project at a board meeting on May 11.

Doubts grow over hitting the zero-carbon target

According to existing plans, 2025 is to be a pivotal moment in the history of British energy. The problem is that while the closure of coal power plants is accelerating, the prospect of Hinkley Point opening by 2025 appears to be receding.

In the paper, the EDF engineers called for a joint “Franco-British project” to commission four to six “optimised EPRs” by the end of the decade that could be operational between 2028 and 2031.

One person with knowledge of the company likened the current EPR to the Concorde supersonic airliner, a technical marvel but a commercial failure. The new EPR would be “more like an Airbus”, the comparatively simple but successful passenger aircraft.

The paper also addresses wider fears that the Hinkley project will in any case not be completed by 2025 and might suffer years of construction delays.
One person on the EDF board who had read the white paper said: “Few believe that we can build this [Hinkley Point] by 2025 any more.”

Another person close to the group said that 2025 was set to remain the official target, but the final decision could incorporate a margin for error because even with a two-year delay the project would still be profitable.
Three people close to the company said that CGN, EDF’s Chinese partner for Hinkley, also feared possible delays, attempting to insert a clause so it would take on a lower financial risk if there were a large problem.
Nuclear options

Engineers believe 4-6 smaller, simpler power plants could become operational as early as 2028, only a year later than the backstop date for Hinkley. UK ministers should consider this option.

In the case of a £5bn cost overrun, despite EDF having a 66.5 per cent stake in the project, EDF would be liable for 80 per cent of the additional costs, according to a document sent by the EDF finance department to the board’s audit committee in January.

That figure could be subject to change as the final investment decision has not been made. EDF declined to comment on the number.

The Hinkley project is still likely to go ahead as planned. Three out of the four EDF unions with board seats are against the project in its current form, as well as at least one independent board member.

But the majority of the 18-strong board is likely to vote in favour of the deal in May, according to people close to the group. The company is 85 per cent state owned, and the government wants the project to go ahead.

http://nicosiamoneynews.com/2016/03/29/edf-dissenters-urge-hinkley-nuclear-delay/