South West Water progress report:
Last night we successfully commenced UV treatment at our Boohay supply tank. This follows the UV being operational at our Hillhead supply tank from 4 June.
The successful commissioning of this additional UV installation means that we now have a double layer of protection using UV and specialist microfilters across the Hillhead and Boohay water supply networks, to prevent any reintroduction of crypto into the network.
We are pleased to say that progress is also being made in cleaning the network, through flushing and ice pigging across the network, targeting areas identified for further work through our sampling programme.