Budleigh Salterton – onshore cable consultation to 5 September 2016 – questions to be answered

Here is the consultation letter and, below it, the maps showing the two possible routes that it might follow onshore.  Also details of where and when representatives of the project will be available for questioning.

Several points spring to mind:

How wide will trenches be?
Will roads need to be closed and, if so, for how long?
How big is the converter station?
Why are some of the cables put in fields, yet others are embedded in roads? Roads particularly affected are the B3178 disrupting Budleigh Salterton, East Budleigh and Colaton Raleigh and the B3184 to the airport, Many other key strategic routes will also be cut across and possibly interrupted, including the A30 and also the railway line.
The two routes out of Budleigh Salterton are very sensitive environmental areas – moleing underground was originally mentioned but seems to have been dropped

The consultation letter (followed by maps of alternative routes included with the letter)

I am writing to invite you to take part a public consultation on proposals to build a 220 kilometre underground and subsea electricity interconnector and converter station which will see power flowing between France, the Channel Island of Alderney, and East Devon.

The FAB Project has the approval of the UK energy regulator Ofgem to build the interconnector, linking the British electricity grid from the existing National Grid substation at Broadclyst to the French grid to help ensure the security of supply to both the UK and the continent. Alderney Renewable Energy (ARE) and Transmission Investment LLP formed a joint venture company, FAB Link, and FAB Link is working with the French grid company RTE – Reseau de Transport d’Electricite – to develop the FAB Project.

The project also intends to take advantage of proposed tidal generators in Alderney to provide reliable, sustainable and low-carbon electricity for consumers on both sides of the Channel, hence the FAB name, which stands for France-Alderney-Britain. It is also our intention to increase competition in electricity markets, cutting prices for consumers.

As shown in the enclosed maps, the cables would come ashore in Britain at Budleigh Salterton and thereafter would run underground between the coast and a new above-ground converter station.

The interconnector cables would run completely underground between the coast and a new above-ground converter station to be built near Exeter International Airport. From the converter station the high-voltage DC electricity transmitted through the interconnector would be converted to or from high-voltage AC current used by the National Grid. Further underground cables would then link up with the grid at Broadclyst. There will be no pylons associated with the FAB Project, and our intention is that we will leave the environment along the route exactly as we found it.

We are holding three public consultation events in East Devon and one public consultation event in Alderney where we will be able to explain our project in more detail. Each of the events is open to the public from 2pm to 8pm. They are:
• Tuesday, 26th July, 2016: Temple Methodist Church Hall, Budleigh Salterton;
• Wednesday, 27th July, 2016: Younghayes Centre, Cranbrook;
• Thursday, 28th July 2016: Woodbury Park Hotel, Woodbury;

The events will provide you with opportunities to express your views on the project. The opinions of all stakeholders will help to inform our proposals for the route of the interconnector and the construction of the converter station before the relevant planning applications are submitted to the relevant authorities at the end of 2016.

If you are not able to attend one of the events, please visit our website to learn more. Copies of the detailed plans, technical reports and environmental appraisals of the onshore and offshore proposals available at the public consultation events will also be available online at http://www.fablink.net from 25th July, and there will be opportunities to express your opinions via the website, phone or by post. The consultation will run until 5th September 2016.

If you do not have access to the internet the information will also be available to view at Budleigh Salterton Library in Station Road, Budleigh Salterton, EX9 6RH, from 25th July to 5th September during normal library opening hours, which are currently 09.30-18.00 on Mondays, 09.30-13.00 on Wednesdays, 09.30-17.30 on Thursdays, and 09.30-13.00 on Fridays and Saturdays. Please note the library is not open on Tuesdays or Sundays.

Route 1

8 x 10 in. (1)

Route 2:

8 x 10 in. (1)