“Britain’s switch to greener energy will take another significant step forward this week with the opening of an industrial-scale battery site in Sheffield.

E.ON said the facility, which is next to an existing power plant and has the equivalent capacity of half a million phone batteries, marked a milestone in its efforts to develop storage for electricity from windfarms, nuclear reactors and gas power stations.

The plant, housed in four shipping containers, is the type of project hailed by the business secretary, Greg Clark, as crucial to transforming the UK’s energy system and making it greener.

At 10MW, the Blackburn Meadows battery is one of the biggest in Britain so far, but will soon be eclipsed by much larger plants.

Centrica, the parent company of British Gas, is building a 49MW facility on the site of a former power station in Barrow-in-Furness, Cumbria, while EDF Energy is working on one of the same size at its West Burton gas power station in Nottinghamshire.

David Topping, the director of business, heat and power solutions at E.ON, said: “This is a milestone for E.ON in the new energy world and an important recognition of the enormous potential for battery solutions in the UK.”

The utility-scale batteries are being built in response to a request from National Grid, the owner of Britain’s power transmission network, for contracts to help it keep electricity supply and demand in balance, which is posing an increasing challenge for the grid as more intermittent wind and solar comes online. …”