See pages 12-18 here:
What a mess! Houses but no road?
Recommendations:
“That Members:
1. Accept that it is not going to be possible to progress with the Housing Infrastructure Fund bid as things stand and that the offer is likely to be withdrawn unless Homes England change their position on land values
2. Re-engage the consultants for the Axminster Urban Extension Masterplan to:
a) review options to enable as much of the development in the masterplan to proceed accepting that this would be ahead of delivery of the relief road in its entirety
b) update the viability of the project to reflect the latest cost estimates and funding position
c) consider the re-phasing of the development in light of the failure of the HIF bid
3. Agree that a Housing Delivery Action Plan be produced to consider how to bolster the housing land supply position in the district and that this be considered by Strategic Planning Committee alongside a revised Axminster Masterplan.”
One thought on “Axminster ‘Master Plan’ – back to the drawing board but don’t upset the developers!”